India's peak power demand topped 270 GW for the first time, roughly 70% higher
than a decade ago. Installed capacity has nearly doubled over 10 years to about
552 GW, with non‑fossil sources now exceeding 300 GW. The government plans
roughly $109bn of transmission investment through 2032, but grid build‑out is
slower and more complex than solar plant construction: transmission corridors
require land, rights‑of‑way, towers, transformers and multiple approvals, and
incomplete towers can stall entire lines. Generation growth has kept pace with
demand growth, but delivery constraints heighten near-term demand for
transmission, storage and financially sustainable distribution to make power
available where and when needed.