Reportedly, TSMC is accelerating construction of a 1.4nm fab at the Central
Taiwan Science Park. The first P1 plant is expected to begin trial runs in April
next year, and volume production is now anticipated in H2 2027, ahead of an
earlier 2028 target. Two temporary on-site offices are being installed for April
completion, with an initial intake of over 5,400 operations and outsourced
staff, sources said.