CGN's 50 MW Gaize (Ngari) wind project in Tibet has completed turbine
installation and entered grid-commissioning, with grid connection planned by
end-2026. The project is undergoing quality acceptance and step-up substation
equipment testing; at full capacity it should generate about 180 GWh/yr and cut
Roughly 150,000 tons of CO2, helping to close a local clean-energy supply gap.