Xibaipo Power Phase IV Unit 7 auxiliary power system was energized successfully on first attempt. Electrical parameters are normal and protection and monitoring signals are operating correctly. The energization covered the 500 kV expansion bus, expansion string switchgear, standby transformer main equipment, the unit high-voltage bus and associated protection and control systems. This follows handover of the main plant and placement of the generator stator, marking another construction milestone

2026-06-02

Xibaipo Power Phase IV Unit 7 auxiliary power system was energized successfully on first attempt. Electrical parameters are normal and protection and monitoring signals are operating correctly. The energization covered the 500 kV expansion bus, expansion string switchgear, standby transformer main equipment, the unit high-voltage bus and associated protection and control systems. This follows handover of the main plant and placement of the generator stator, marking another construction milestone for the project.