Japan’s largest power producer JERA has signed a memorandum with Dell (DELL.N)
and UK AI-infrastructure developer RHAELM to create a standardized framework for
Nationwide AI infrastructure, with the first project sited in Chiba. JERA will
provide land adjacent to its Chiba power plant and commit 400MW of power
capacity under a 15–25 year agreement. RHAELM will develop, build, operate and
finance a hyperscale AI data center targeted to reach 400MW full capacity in
2029 with phased commissioning from 2028. Dell will supply standardized
rack-level AI infrastructure.